Water System Improvement Project
|
|
Client:
Cabazon County Water District
   
(909) 849-4442 | Construction Cost Information:
Original Contract: $4,193,800
Contract Change Orders: <$125,800>
Change Order Percentage: <3.0%>
Final Construction Cost: $4,068,000 |
|
The project consisted of the construction of the first significant improvements to the District's Water system in over 30 years.
The new facilities allowed the district to lift a seven year moratorium on new water service, which is already leading to the community's
economic revitalization through the redevelopment of certain blighted areas and the development of new commercial ventures. Facilities
constructed include two 1,000 GPM wells, two 1.0 MG welded steel water storage reservoirs, and 32,500± L.F. of 16" and 12" transmission
pipeline.
| | |
Krieger & Stewart
Provided the following services:
PRELIMINARY SERVICES
Project Financing
Preliminary Design
Site and Alignment Selection
Environmental Assessment/
CEQA Compliance
Equipment Selection
DESIGN ENGINEERING
Surveying
Facility and Site Design
Structural, Mechanical, and Electrical Engineering
Contract Document Preparation
Bidding Phase Support
CONSTRUCTION ENGINEERING
Contract Administration
Submittals Review
Construction Surveying and
Observation
Warranty Period Inspections
|
| © 1997 Krieger & Stewart, Incorporated
|