Water Supply Improvement Project Phases I, II, and III
|
|
Client:
Indian Wells Valley Water District
LeRoy O. Tucker, Assistant General Manager
(760) 375-5089 | Construction Cost Information:
Original Contract: $2,909,100
Contract Change Orders: $17,500
Change Order Percentage: 0.6%
Final Construction Cost: $2,926,600 |
|
The project consisted of the construction of 39,000± L.F. of 30" pipeline and 5,000± L.F. of 24" pipeline,
along with a number of appurtenances and connections to existing District facilities. The pipeline conveys water
from a well field on the District's westerly boundary to the District's primary service area in the City of
Ridgecrest. The project was constructed within and/or adjacent to lands under the jurisdiction of a number of agencies,
including the U.S. Navy, Caltrans, Kern County, and the City of Ridgecrest, making for a complicated alignment
selection and encroachment permit acquisition process.
| | |
Krieger & Stewart
Provided the following services:
PRELIMINARY SERVICES
Project Financing
Alignment Selection
Environmental Assessment/
CEQA Compliance
Right-of-Way and Encroachment
Permit Acquisition
DESIGN ENGINEERING
Surveying
Hydaulic Surge Analyses
Conflicting Utility Excavation/Verification
Contract Document Preparation
Bidding Phase Support
CONSTRUCTION ENGINEERING
Contract Administration
Submittals Review
Construction Surveying and
Observation
Acceptance (Final) Inspection
|